Sizing a UPS starts with two numbers: how much power your equipment draws, measured in watts, and how long you need it to keep running during an outage, the runtime. Once you have those, three more factors decide the final specification: whether the supply is single-phase or three-phase, the environment the UPS will live in, and how much you expect the load to grow. Get all of this right and the UPS is invisible, which is the point. Get it wrong and you have either overpaid for capacity you never use, or fitted a unit that gives out at the worst moment. This guide works through each part, with worked examples, so you can brief a supplier properly or sense-check a quote. You can also look at this guide for Total cost of ownership
How do you work out the load a UPS has to carry?
The load is the total power your connected equipment draws, and the figure that matters is watts (W), the real power. List everything you want to protect and add up the draw of each item: each server, the storage, the network switch, the firewall, the comms gear. You will usually find the figure on the device label, in its spec sheet, or from the power-supply rating. The nameplate rating is the maximum the device could draw, which is often well above what it actually pulls in normal use, so where you can measure the real draw with a meter or a PDU, use that instead, because sizing to nameplate alone tends to oversize the UPS.
There is one trap worth knowing. UPS units are rated in both VA (volt-amps, the apparent power) and watts (the real power), and the watt rating is the one that limits you. A UPS sold as “3000VA / 2700W” can carry 2700W of real load, not 3000W. Older equipment had a power factor around 0.8, so VA and watts differed a lot; modern IT runs close to a power factor of 1.0, which is why current Eaton units quote watts and VA almost equal. Always size against the watt rating, and against your real measured load where you have it.
How long does the runtime need to be?
Runtime is how long the UPS holds the load on battery, and the right target depends on what you need to happen during an outage. There are three common goals. The first is a clean shutdown: just long enough for servers to close down gracefully or staff to save and stop, often five to ten minutes. The second is ride-through: long enough to carry the load across the short outages that make up most real-world events, so the equipment never goes down at all, perhaps fifteen to thirty minutes. The third is bridge-to-generator: enough runtime for a standby generator to detect the outage, start and take over, usually only a minute or two, after which the generator carries the load.
Runtime is not free. More runtime means more battery, which means more cost and more space, so be honest about what you actually need. Paying for an hour of battery when your real requirement is a clean shutdown is waste; beyond a point, a generator is the better and cheaper answer than ever-larger battery banks. Decide the goal first, then size the battery to it.
How do you extend runtime with battery modules?
When you need more runtime than a UPS gives on its internal batteries, you add extended battery modules. An extended battery module (EBM), sometimes called a battery cabinet or pack, is an external set of batteries that plugs into the UPS to increase how long it can hold the load. This is the usual way to reach fifteen, thirty or sixty minutes of runtime without moving to a much larger UPS. Eaton units are built for it: the 9SX Gen2, 9PX and 5PX Gen2 all accept one or more add-on EBMs, and larger systems like the 93PS use external battery cabinets sized to the runtime you need.
Two practical points come with EBMs. First, the UPS charger has to be rated to recharge the extra batteries in a sensible time; add several modules and the standard charger may take a long while to bring them back to full after an outage, so a larger charger or a unit designed for the battery count is sometimes needed. Second, more battery means more weight and floor space, and the runtime you gain is not perfectly linear, so the right number of modules is a calculation, not a guess. We use the manufacturer runtime tables to match the EBM count to your target rather than rounding up.
Single-phase or three-phase: which supply do you have?
Most racks, offices and small server rooms run on a single-phase supply, and a single-phase UPS like the Eaton 5P, 5PX, 9SX or 9PX is the right fit. Larger sites, bigger loads and many purpose-built server rooms run on a three-phase supply, where a three-phase UPS such as the 93PS is built to match. There is also a middle option: some installations take a three-phase input and deliver a single-phase output (a 3:1 configuration), which can balance the draw better across the building supply and suits sites that have three-phase available but mostly single-phase equipment.
Phase matters for more than just the connector. Three-phase systems generally suit larger loads, scale further, and pair more cleanly with standby generators, which are usually three-phase themselves. If you are not sure what you have, the incoming distribution board will tell you, and it is worth confirming before sizing, because it changes which model range you are choosing from. We check the supply, the load profile and any generator on site, and specify the phase configuration around them.
Find the Right Eaton UPS
Does the environment change the sizing?
Yes, and it is the part most people miss. A UPS and its batteries are rated for a specific environment, and the room they sit in directly affects both how long the batteries last and how much capacity the unit can deliver. The biggest factor is temperature. Battery life is rated at around 20 to 25 degrees Celsius, and every 10 degrees above that can roughly halve the service life of the battery, so a UPS in a hot, unventilated cupboard will need its batteries replaced far sooner than one in a cool, airy comms room. If the space runs warm, plan for shorter battery life or improve the cooling, and never box a UPS into a sealed enclosure with no airflow.
Two other conditions can matter. Altitude derates a UPS, because thinner air cools it less effectively, so above roughly 1000 metres the unit can deliver less than its rated power; in Malta this rarely bites, but it is worth knowing if equipment is specified for a high-altitude site. Humidity and dust matter too: damp, salty or dusty air shortens the life of electronics, so a UPS near the coast or on a workshop floor should be sited and, if needed, protected accordingly. The short version is that where you put the UPS is part of sizing it, not an afterthought, and we factor the real conditions of the room into the specification.
How much headroom should you leave for growth?
Size the UPS to run at roughly 70 to 80 percent of its watt rating at your current load, not at 100 percent. That headroom does two things: it leaves room to add equipment without replacing the UPS, and it keeps the unit off its absolute limit, which is better for efficiency and battery life. If you know a new server or a second rack is coming, factor it in now, because adding capacity later is far cheaper than swapping the whole unit. Equally, do not over-provision on a vague guess; a sensible 20 to 30 percent margin is the balance between future-proofing and paying for nothing.
Worked examples
A small comms rack. Two servers at 300W each, a storage unit at 200W, a switch at 100W and a firewall at 50W give a total of 950W. Add headroom so the UPS runs at about 75 percent and you need roughly 1300W or more. If the goal is a clean shutdown of ten minutes, a line-interactive Eaton 5PX Gen2 in the 1500 to 2000VA class covers it, sited in a ventilated cabinet.
A server room needing thirty minutes. Take the same 950W load but a requirement to ride through longer outages for half an hour. Here an online Eaton 9SX Gen2 sized for the load, plus one or two extended battery modules to reach the thirty-minute target, is the right shape, with the charger checked so the batteries recharge in good time after an event.
A three-phase server room. A purpose-built room drawing 20kW on a three-phase supply, with a standby generator, calls for a three-phase online Eaton 93PS sized with headroom, with only a short bridge-to-generator runtime because the generator carries the load after a minute or two. The method is identical to the small rack; only the numbers and the phase change.
What are the common sizing mistakes?
A handful come up again and again. Sizing against VA instead of watts, and ending up with a unit that cannot carry the real load. Sizing to nameplate ratings rather than measured draw, and overspending on a unit far bigger than the load needs. Forgetting that the battery ages, so the thirty minutes you sized for quietly becomes fifteen by year four unless you plan battery replacement. Adding extended battery modules without checking the charger can recharge them in a reasonable time. Putting the UPS in a hot cupboard and then wondering why the batteries fail early. And leaving no headroom, so the next server tips the unit over its limit. Every one of these is avoidable with a few minutes of arithmetic and a look at the room.
Line-interactive or online at that size?
Sizing tells you how big; topology tells you which type. A line-interactive UPS switches to battery in a few milliseconds, which is fine for most IT and costs less; an online double-conversion UPS rebuilds the power continuously with no transfer gap, which is what sensitive servers, storage and databases need. Use online where a momentary gap would cause real damage, and line-interactive everywhere else. Our UPS and power protection hub maps each scenario and tier to the right Eaton model once you know your load, runtime, phase and environment.
Let Sirap size it with you
If you tell us what is in the rack, what you need to happen during an outage, whether the supply is single or three-phase, and where the unit will sit, we will size the UPS, the battery and any extended modules properly rather than rounding up to be safe, and match it to the right Eaton model. We supply, install and maintain it, including planned battery service, from a team based here in Malta. See the full range on our UPS and power protection page, or get in touch to size your system.
Featured Products in this article
-

Synology FlashStation FS200T Compact 6-bay All-Flash NAS
Read more -

Synology PAS7700 Active-Active NVMe Enterprise Storage
Read more -

Synology RackStation RS4826xs+ 12-Bay Rackmount NAS
Read more -

Synology RackStation RS3626xs+ 12-Bay Rackmount NAS
Read more -

Synology RackStation RS1626xs+ 4-Bay Rackmount NAS
Read more -

Synology RackStation SA3200D 12-Bay Dual Controller Rackmount NAS
Read more -

Synology RackStation RS2825RP+ 16-Bay Rackmount NAS
Read more -

Synology ActiveProtect Applicance DP7200
Read more -

Synology RackStation SA3400D 12-Bay Dual Controller Rackmount NAS
Read more -

Synology RackStation RS4021xs+ 16-Bay Rackmount NAS
Read more -

Synology RackStation RS1619xs+ 4-Bay Rackmount NAS
Read more -

Synology RackStation RS1221+ & RS1221RP+ 8-Bay Rackmount NAS
Read more
Kurt Paris
With an MSc in Software Engineering, and over 15 years in IT Management, Kurt Paris leads technology strategy at Sirap. Zebra Technologies, Domino and Cisco-certified, he helps Maltese businesses build resilient storage & backup infrastructure, Machine Vision & AutoID Automation

